Question 76 - C_S43_2023 discussion

Report
Export

You cancel the technical completion of a work order. What are the effects? Note: There are 2 correct answers to this question?

A.

Open reservations are recompiled.

Answers
A.

Open reservations are recompiled.

B.

Open purchase requisitions are recompiled

Answers
B.

Open purchase requisitions are recompiled

C.

Referenced notifications are put in Process again.

Answers
C.

Referenced notifications are put in Process again.

D.

Open purchase orders are recompiled.

Answers
D.

Open purchase orders are recompiled.

Suggested answer: A, B