The planner adds stock materials in the maintenance order. What are possible options for handling of reservations within a maintenance order? Note: There are 2 correct answers to this question
A.
Open reservations can be cleared when a maintenance order operation is finally confirmed.
B.
Reservations are created only after a material availability check has been performed
C.
For the combination of order type and planner group, you can decide when reservations are created
D.
All open reservations are closed when the maintenance order is set to TECO.