In SAP Central Business Configuration, which activities can you perform in the Product-Specific Configuration Phase? Note: There are 3 correct answers to this question.
A.
Add blocking reasons for billing.
B.
Create new scope items.
C.
Change approval thresholds.
D.
Add new sales organizations.
E.
Modify building blocks.