Your customer wants to use batch management in SAP Extended Warehouse Management (SAP EWM). When do you have to create a batch during the inbound process?

A.

Before the goods receipt is posted in SAP EWM

Answers
A.

Before the goods receipt is posted in SAP EWM

B.

Before the inbound delivery is created in SAP EWM

Answers
B.

Before the inbound delivery is created in SAP EWM

C.

Before the inbound delivery is created in SAP ERP

Answers
C.

Before the inbound delivery is created in SAP ERP

D.

Before the inbound delivery is distributed from SAP ERP to SAP EWM

Answers
D.

Before the inbound delivery is distributed from SAP ERP to SAP EWM

Suggested answer: C