Question 22 - C_TFG61_2405 discussion
How does an SOW bid approval process differ from the SOW approval process? Note: There are 3 correct answers to this question.
A.
When an SOW Bid approval is required, those steps take place first before the SOW Module is engaged.
B.
The remainder of the workflow after SOW Bids contains a classification, a supplier, and an SOW template.
C.
The first steps for creating an SOW Bid are choosing the Classification and the Template, but the option to choose a supplier is not available.
D.
The details of the SOW Bid will generate Details, Clauses, Characteristics, and SOW Workers.
E.
After the SOW Bid has been populated and approved, it gets sent to multiple suppliers.
Your answer: