In a project, what is the correct term for a group of dependencies, activities, and relationships sequenced in chronological order?

A.

Work breakdown structure

Answers
A.

Work breakdown structure

B.

Project planning

Answers
B.

Project planning

C.

Routing

Answers
C.

Routing

D.

Network

Answers
D.

Network

Suggested answer: D

Explanation:

In the context of project management within SAP, the correct term for a group of dependencies, activities, and relationships sequenced in chronological order is a Network (D). Networks are used to represent the logical and temporal sequence of tasks within a project, enabling detailed planning, execution, and monitoring of project activities.

A Work Breakdown Structure (A) is used to structure the project into manageable sections, but it does not inherently define the chronological sequence of activities.

Project Planning (B) is a broad term that encompasses all aspects of planning within a project, including the creation of networks and work breakdown structures, but it is not a specific object or element within SAP.

Routing (C) is more commonly associated with manufacturing processes in SAP and defines the sequence of operations required to produce a product.