Which of the following documents would explain the consequences of server downtime?

A.

Service-level agreement

Answers
A.

Service-level agreement

B.

Business continuity plan

Answers
B.

Business continuity plan

C.

Disaster recovery plan

Answers
C.

Disaster recovery plan

D.

Business impact analysis

Answers
D.

Business impact analysis

Suggested answer: D

Explanation:

A business impact analysis (BIA) is a document that outlines the potential effects of downtime on business operations. It identifies critical business functions and estimates the impact of disruption on the organization's ability to function.

Business impact analysis (Answer D): This document is specifically designed to assess the consequences of downtime and other disruptions.

Service-level agreement (Option A): Defines the expected level of service between a provider and a client but doesn't directly explain downtime consequences.

Business continuity plan (Option B): Outlines how the business will continue operating during a disruption but doesn't focus solely on the consequences of downtime.

Disaster recovery plan (Option C): Focuses on restoring systems after a disaster but doesn't outline the specific impact of downtime.

CompTIA Server+

Reference:

This topic relates to SK0-005 Objective 4.1: Explain disaster recovery concepts.