Question 136 - COBIT 2019 discussion

Report
Export

Which of the following is an important desired outcome to be achieved from the execution of an EGIT implementation program plan?

A.

Completion of EGIT project implementation regardless of the amount of time required

Answers
A.

Completion of EGIT project implementation regardless of the amount of time required

B.

Transition of EGIT projects into the enterprise's normal development life cycle

Answers
B.

Transition of EGIT projects into the enterprise's normal development life cycle

C.

Development of a record of unapproved EGIT projects

Answers
C.

Development of a record of unapproved EGIT projects

D.

Mitigation of all risks associated with the implementation of EGIT projects

Answers
D.

Mitigation of all risks associated with the implementation of EGIT projects

Suggested answer: B

Explanation:

The desired outcome of an EGIT implementation program plan is to ensure that the EGIT projects are aligned with the enterprise's strategy, objectives, and stakeholder needs, and that they deliver value and benefits to the enterprise. One of the key steps in achieving this outcome is to transition the EGIT projects into the enterprise's normal development life cycle, which involves ensuring that the projects are integrated with the existing processes, systems, and governance structures, and that they are monitored and controlled for quality, performance, and risk.This will also facilitate the continuous improvement and adaptation of the EGIT projects to changing business needs and environment12Reference:1: COBIT 2019 Implementation Guide, page 49-502: COBIT 2019 Design Guide, page 67-68