An enterprise has hired a consultant to resolve the issue of multiple IT-enabled change initiatives frequently being delivered late and failing to meet business needs. Which of the following management objectives from the COBIT core model is BEST for the consultant to recommend for developing a governance and management system?

A.

DSS03 Managed Problems

Answers
A.

DSS03 Managed Problems

B.

APO10 Managed Vendors

Answers
B.

APO10 Managed Vendors

C.

AP014 Managed Data

Answers
C.

AP014 Managed Data

D.

BAI11 Managed Projects

Answers
D.

BAI11 Managed Projects

Suggested answer: D

Explanation:

The management objective BAI11 Managed Projects involves ensuring that IT-enabled change initiatives are delivered on time, within budget, and in accordance with stakeholder expectations. This management objective covers the activities of initiating, planning, executing, monitoring, controlling, and closing IT projects, as well as managing project risks, issues, quality, scope, resources, communications, and stakeholders. This management objective is best for the consultant to recommend for developing a governance and management system that can address the issue of multiple IT-enabled change initiatives frequently being delivered late and failing to meet business needs.By applying this management objective, the enterprise can improve its project governance and management capabilities, ensure alignment of IT projects with business strategy and objectives, enhance project performance and outcomes, and increase stakeholder satisfaction and value realization12Reference:1: COBIT 2019 Process Reference Guide: Governance and Management Objectives, page 77-792: COBIT 2019 Implementation Guide: page 49-50