At which stage of the EGIT implementation life cycle should the enterprise determine the impact of an improvement program on IT and the business and how to maintain the improvement momentum?

A.

When defining the EGIT implementation road map

Answers
A.

When defining the EGIT implementation road map

B.

When developing the EGIT implementation program plan

Answers
B.

When developing the EGIT implementation program plan

C.

When executing the EGIT implementation program plan

Answers
C.

When executing the EGIT implementation program plan

D.

When initiating an EGIT program

Answers
D.

When initiating an EGIT program

Suggested answer: B

Explanation:

The EGIT implementation life cycle consists of four stages: initiating an EGIT program, defining the EGIT implementation road map, developing the EGIT implementation program plan, and executing the EGIT implementation program plan. The third stage, developing the EGIT implementation program plan, involves identifying and defining the success metrics for the EGIT continual improvement program. These metrics should be aligned with the enterprise goals and objectives, and should measure the performance and outcomes of the EGIT processes and practices.The success metrics should also be SMART (specific, measurable, achievable, relevant, and time-bound), and should be communicated to all stakeholders involved in the EGIT program.Reference:: COBIT 2019 Design Guide: Designing an Information & Technology Governance Solution, page 261: COBIT 2019 Design Guide: Designing an Information & Technology Governance Solution, page 41