Question 178 - COBIT 2019 discussion
Who is responsible for performing a stakeholder satisfaction survey and gathering feedback on lessons learned from the implementation of an EGIT program plan?
A.
The CIO and the program steering committee
B.
Business executives and the l&I governance board
C.
IT managers and IT process owners
D.
The risk and compliance function and IT audit