Question 41 - CPIM-Part-2 discussion
The demonstrated capacity of equipment in a process flow is $1,200 per day. Due to a malfunction in a feeder line, utilization of the equipment is reduced by 25% on Day 6. If the efficiency remains unchanged at 110%, what would the output be on Day 6?
A.
$300
B.
$330
C.
$900
D.
$990
Your answer: