ExamGecko
Question list
Search
Search

Question 77 - CPIM-Part-2 discussion

Report
Export

The results from responding to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes is called:

A.
bullwhip effect.
Answers
A.
bullwhip effect.
B.
supply and demand.
Answers
B.
supply and demand.
C.
process train.
Answers
C.
process train.
D.
forward integration.
Answers
D.
forward integration.
Suggested answer: A

Explanation:

The results from responding to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes is called the bullwhip effect. The bullwhip effect is a phenomenon that occurs when small changes in demand at the downstream end of the supply chain (such as retailers or customers) cause larger and larger fluctuations in demand at the upstream end of the supply chain (such as wholesalers, distributors, or manufacturers). The bullwhip effect can create inefficiencies, waste, and costs in the supply chain, as well as reduce customer satisfaction and profitability.

One of the causes of the bullwhip effect is the response to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes. Lead time is the time between placing an order and receiving it from a supplier. Lot size is the quantity of units ordered or produced at a time. When there is uncertainty or variability in demand or supply, such as due to seasonality, promotions, disruptions, or forecasting errors, some supply chain members may try to cope by exaggerating lead times and increasing lot sizes. For example, a retailer may increase its safety stock or reorder point to avoid stockouts or delays, or a manufacturer may produce more than needed to take advantage of economies of scale or discounts. However, these actions can have unintended consequences, as they can distort the demand information and amplify the demand variability along the supply chain. This can result in excess inventory, low inventory turnover, high holding costs, poor service levels, lost sales, obsolete products, or capacity issues.

To prevent or reduce the bullwhip effect caused by responding to uncertainty in the supply chain by exaggerating lead times and increasing lot sizes, some possible solutions are:

Improving communication and collaboration among supply chain members to share accurate and timely demand information and forecasts.

Reducing lead times and lot sizes by using lean production techniques, just-in-time inventory systems, or quick response methods.

Implementing vendor-managed inventory (VMI) systems, where suppliers are responsible for managing and replenishing the inventory of their customers based on their actual consumption data.

Adopting advanced technologies, such as radio-frequency identification (RFID), artificial intelligence (AI), or blockchain, to enhance visibility, traceability, and coordination in the supply chain.