In a make-to-order (MTO) environment, inputs to sales and operations planning (S&0P) should include the:

A.
projected backlog of customer orders.
Answers
A.
projected backlog of customer orders.
B.
work-in-process (WIP) inventory.
Answers
B.
work-in-process (WIP) inventory.
C.
finished goods inventory.
Answers
C.
finished goods inventory.
D.
available-to-promise (ATP) data.
Answers
D.
available-to-promise (ATP) data.
Suggested answer: A

Explanation:

In a make-to-order (MTO) environment, the production process is triggered by customer orders, which means there is no finished goods inventory or work-in-process inventory to consider in the sales and operations planning (S&OP) process. The available-to-promise (ATP) data is not an input to the S&OP process, but rather an output that indicates the quantity and date of products that can be promised to customers based on the current supply plan. The projected backlog of customer orders, on the other hand, is an important input to the S&OP process, as it reflects the current and future demand for the products and services offered by the organization. The projected backlog can help the organization plan its capacity, resources, materials, and delivery schedules to meet customer expectations and optimize profitability.Reference: CPIM Part 2 Exam Content Manual, Domain 3: Plan and Manage Demand, Section 3.1: Demand Management Concepts and Tools, p. 27-28.