Question 132 - CPIM-Part-2 discussion
A firm produces a moderate variety of products to stock in a single plant. The plant is organized in a functional layout with some work cells. Which of the following indicators most appropriately would be used to evaluate the effectiveness of the detailed capacity planning processes?
A.
Units of output per direct labor hour
B.
Change in level of work-in-process (WIP) inventory
C.
Percentage of master schedule attained
D.
Level of finished goods inventory