Which of the following activities is the most appropriate use of an advanced planning and scheduling system?

A.
Selecting the target market for a product
Answers
A.
Selecting the target market for a product
B.
Optimizing transportation routes
Answers
B.
Optimizing transportation routes
C.
Creating a daily demand forecast
Answers
C.
Creating a daily demand forecast
D.
Identifying constraints within a facility
Answers
D.
Identifying constraints within a facility
Suggested answer: D

Explanation:

An advanced planning and scheduling (APS) system is designed to enhance the efficiency and effectiveness of the production process. Its primary functions include:

Constraint Identification: APS systems are highly effective at identifying constraints within a facility, such as bottlenecks, capacity limits, and material shortages. By pinpointing these constraints, the system helps in planning and optimizing the use of available resources.

Production Optimization: They optimize scheduling by considering various constraints and ensuring that production schedules align with capacity and material availability.

Scenario Analysis: APS systems allow for the simulation of different production scenarios to determine the best course of action in response to changing conditions.

Real-Time Adjustments: They provide real-time data and feedback, enabling quick adjustments to production plans to address issues as they arise.

'Advanced Planning and Scheduling in Manufacturing and Supply Chain Management' by Hermann Meyr, Marc Salomon, and Carlo Veilleux

APICS, 'Advanced Planning and Scheduling Systems: An Overview'