The diagram below shows the process of manufacturing of item D and the capacity of each operation. Each operation requires one unit from the previous step.

Which of the following is the total production throughput?

A.
25 units/hr.
Answers
A.
25 units/hr.
B.
27 units/hr.
Answers
B.
27 units/hr.
C.
65 units/hr.
Answers
C.
65 units/hr.
D.
84 units/hr.
Answers
D.
84 units/hr.
Suggested answer: A

Explanation:

To determine the total production throughput, identify the bottleneck operation, which is the operation with the lowest capacity:

Operation A: 32 units/hr

Operation B: 25 units/hr

Operation C: 40 units/hr

Operation D: 27 units/hr

Operation B has the lowest capacity at 25 units/hr, making it the bottleneck. The total production throughput is limited by this bottleneck operation, which is 25 units/hr.

Goldratt, E. M., & Cox, J. (1984). The Goal: A Process of Ongoing Improvement. North River Press.

Hopp, W. J., & Spearman, M. L. (2011). Factory Physics. Waveland Press.

asked 16/09/2024
Mathijn Smit
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first