In the Supply Chain Operations Reference (SCOR) model, which of the following metrics measures responsiveness of a supply chain?

A.
On-time delivery
Answers
A.
On-time delivery
B.
Perfect order fulfillment
Answers
B.
Perfect order fulfillment
C.
Order fulfillment cycle time
Answers
C.
Order fulfillment cycle time
D.
Total inventory days of supply
Answers
D.
Total inventory days of supply
Suggested answer: C

Explanation:

In the Supply Chain Operations Reference (SCOR) model, the metric that measures responsiveness of a supply chain is the Order Fulfillment Cycle Time. This metric indicates the average time taken to fulfill customer orders from the moment they are placed until delivery. It directly measures how quickly the supply chain can respond to customer demand. On-time delivery and perfect order fulfillment measure reliability, while total inventory days of supply measures efficiency.

Reference: Supply Chain Council, 'Supply Chain Operations Reference (SCOR) Model.