An order with a requested ship date inside the demand time fence (DTF) has been received. There is no inventory available-to-promise (ATP). Which of the following positions is most appropriate to decide whether or not to accept the order?

A.
Order entry representative
Answers
A.
Order entry representative
B.
Sales manager
Answers
B.
Sales manager
C.
Master scheduler
Answers
C.
Master scheduler
D.
Operations manager
Answers
D.
Operations manager
Suggested answer: C

Explanation:

When an order is received with a requested ship date inside the demand time fence (DTF) and there is no available-to-promise (ATP) inventory, the master scheduler is the most appropriate position to decide whether to accept the order. Here's why:

Demand Time Fence (DTF): The DTF is a period during which changes to the master production schedule are restricted to prevent disruption. Orders within this period require careful consideration.

Master Scheduler's Role: The master scheduler has visibility over the production schedule and capacity, making them best positioned to assess the feasibility of fulfilling the order within the given constraints.

Decision-Making: The master scheduler can evaluate the impact on current production, determine if resources can be reallocated, and ensure that accepting the order will not negatively affect other commitments.

Vollmann, T. E., Berry, W. L., Whybark, D. C., & Jacobs, F. R. (2005). Manufacturing Planning and Control for Supply Chain Management. McGraw-Hill.