Bluesky Travel is an independent travel agency specialising in luxury bespoke holidays, which is introducing a new booking process. So far, the following key changes have been made:

1) The new Commercial Off The Shelf (COTS) software package for making bookings has been installed and is working

2) Data is being migrated from the old computer system to the COTS software package

3) The IT department has documented the configuration of the COTS system

4) The legal department has confirmed that the new COTS system is compliant with company policies.

In taking a holistic approach, which of the following areas of the POPII Model have NOT yet been addressed by the changes identified?

A.
Organisation and process.
Answers
A.
Organisation and process.
B.
Process and people
Answers
B.
Process and people
C.
People and technology
Answers
C.
People and technology
D.
Organisation and information.
Answers
D.
Organisation and information.
Suggested answer: A

Explanation:

The elements of the POPII model that have not yet been addressed by the changes identified are organisation and process. This is because there is no mention of how the new booking process will affect the organisational structure, roles, responsibilities, and culture of the company, or how the new COTS software package will integrate with the existing business processes and workflows. These elements are important to consider when introducing a new system or technology, as they may require changes or adaptations to ensure alignment and compatibility. Option A is the correct answer.

POPIT Model Business Analysis Technique - Knowledge Train

POPIT Model - GSU

asked 16/09/2024
Mikael Klingebrant
30 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first