Question 7 - MBP18 discussion
A record company is implementing a new system to replace an existing legacy system. The project has challenging as the new system must be implemented before support for the existing system is withdrawn. The business users have been involved throughout the project and their confidence in the new system is high.
Which implementation approach is the LEAST appropriate in this situation?
A.
Pilot
B.
Phased
C.
Direct changeover
D.
Parallel running.