A business analyst working on a project has identified:

3 requirements for which there is a workaround and the users can live without;

2 requirements that the users can live without for now;

15 requirements which, if not delivered, will make the solution unworkable or useless.

When these requirements are prioritized using MoSCoW, which of the following categories will not be used?

A.
M
Answers
A.
M
B.
S
Answers
B.
S
C.
C
Answers
C.
C
D.
W
Answers
D.
W
Suggested answer: D

Explanation:

Reference: https://www.productplan.com/glossary/moscow-prioritization/