Question 33 - RE18 discussion
A business analyst working on a project has been informed that changes are required in a particular requirement; she has revisited the requirement set and is unable to determine other requirements that might be impacted by such changes.
Which element of requirements management appears to be missing?
A.
Change control
B.
Requirements cross-referencing
C.
Requirements identification
D.
Requirements origin and ownership
Your answer: