A business analyst working on a project has been informed that changes are required in a particular requirement; she has revisited the requirement set and is unable to determine other requirements that might be impacted by such changes.

Which element of requirements management appears to be missing?

A.
Change control
Answers
A.
Change control
B.
Requirements cross-referencing
Answers
B.
Requirements cross-referencing
C.
Requirements identification
Answers
C.
Requirements identification
D.
Requirements origin and ownership
Answers
D.
Requirements origin and ownership
Suggested answer: C
asked 16/09/2024
mostafa khalaf
53 questions