Under which two circumstances will a service be taken out of the slow start phase with automated slow start? (Choose Two)
A.
The Service is receiving more than 480 requests per second
B.
The new service request rate is slower than the actual request rate
C.
The Service does not receive traffic for four successive increment intervals
D.
The request rate has been incremented 200 times
E.
The percentage of traffic that the new service must receive is greater than or equal to 100.