In the early phase of a project, after the project requirements are clarified, the project owner should Checklist to describe the customer's requirements. (Capitalize the first letter of each word.)

A.
Customer Requirement Specification
Answers
A.
Customer Requirement Specification
Suggested answer: A

Explanation:

Customer Requirement Specification (CRS) is a document that needs to be output after the project requirements are clarified. The CRS describes the customer's requirements in detail and serves as the basis for subsequent project design and delivery.

Reference: https://support.huawei.com/enterprise/en/doc/EDOC1100058940/8a8f1c9b/crs