ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 3 - IIA-CIA-Part3 discussion

Report
Export

An internal auditor is reviewing key phases of a software development project. Which of the following would; the auditor most likely use to measure the project team's performance related to how project tasks are completed?

A.
A balanced scorecard.
Answers
A.
A balanced scorecard.
B.
A quality audit
Answers
B.
A quality audit
C.
Earned value analysis.
Answers
C.
Earned value analysis.
D.
Trend analysis
Answers
D.
Trend analysis
Suggested answer: B
asked 18/09/2024
Andrew Staton
26 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first