Question 336 - IIA-CIA-Part3 discussion
Which of the following statements is true regarding a project life cycle?
A.
Risk and uncertainty increase over the life of the project.
B.
Costs and staffing levels are typically high as the project draws to a close.
C.
Costs related to making changes increase as the project approaches completion.
D.
The project life cycle corresponds with the life cycle of the product produced by or modified by the project.
Your answer: