Question 84 - IIA-CIA-Part3 discussion
Which of the following controls would an internal auditor consider the most relevant to reduce risks of project cost overruns?
A.
Scope change requests are reviewed and approved by a manager with a proper level of authority.
B.
Cost overruns are reviewed and approved by a control committee led by the project manager.
C.
There is a formal quality assurance process to review scope change requests before they are implemented
D.
There is a formal process to monitor the status of the project and compare it to the cost baseline