Which of the following controls would an internal auditor consider the most relevant to reduce risks of project cost overruns?

A.
Scope change requests are reviewed and approved by a manager with a proper level of authority.
Answers
A.
Scope change requests are reviewed and approved by a manager with a proper level of authority.
B.
Cost overruns are reviewed and approved by a control committee led by the project manager.
Answers
B.
Cost overruns are reviewed and approved by a control committee led by the project manager.
C.
There is a formal quality assurance process to review scope change requests before they are implemented
Answers
C.
There is a formal quality assurance process to review scope change requests before they are implemented
D.
There is a formal process to monitor the status of the project and compare it to the cost baseline
Answers
D.
There is a formal process to monitor the status of the project and compare it to the cost baseline
Suggested answer: D