According to IIA guidance on IT, which of the following best describes a situation where data backup plans exist to ensure that critical data can be restored at some point in the future, but recovery and restore processes have not been defined?
A.
Hot recovery plan
B.
Warm recovery plan
C.
Cold recovery plan
D.
Absence of recovery plan