Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?

A.
Monte Carlo Analysis.
Answers
A.
Monte Carlo Analysis.
B.
Project Management Information System (PMIS).
Answers
B.
Project Management Information System (PMIS).
C.
Earned Value Management (EVM).
Answers
C.
Earned Value Management (EVM).
D.
Integrated Project Plan
Answers
D.
Integrated Project Plan
Suggested answer: A