Management is designing its disaster recovery plan. In the event that there is significant damage to the organization's IT systems this plan should enable the organization to resume operations at a recovery site after some configuration and data restoration. Which of the following is the ideal solution for management in this scenario?

A.
A warm recovery plan.
Answers
A.
A warm recovery plan.
B.
A cold recovery plan.
Answers
B.
A cold recovery plan.
C.
A hot recovery plan.
Answers
C.
A hot recovery plan.
D.
A manual work processes plan
Answers
D.
A manual work processes plan
Suggested answer: A