At what stage of project integration management would a project manager and project management team typically coordinate the various technical and organizational interfaces that exist in the project?

A.
Project plan development.
Answers
A.
Project plan development.
B.
Project plan execution
Answers
B.
Project plan execution
C.
Integrated change control.
Answers
C.
Integrated change control.
D.
Project quality planning
Answers
D.
Project quality planning
Suggested answer: A