Question 291 - IIA-CIA-Part3 discussion
An organization contracted a third-party service provider to plan, design, and build a new facility.
Senior management would like to transfer all of the risk to the builder. Which type of procurement contract would the organization use?
A.
Cost-plus contract.
B.
Turnkey contract.
C.
Service contract.
D.
Solutions contract.