An organization contracted a third-party service provider to plan, design, and build a new facility.

Senior management would like to transfer all of the risk to the builder. Which type of procurement contract would the organization use?

A.
Cost-plus contract.
Answers
A.
Cost-plus contract.
B.
Turnkey contract.
Answers
B.
Turnkey contract.
C.
Service contract.
Answers
C.
Service contract.
D.
Solutions contract.
Answers
D.
Solutions contract.
Suggested answer: A