Related questions
Question 317 - IIA-CIA-Part3 discussion
A organization finalized a contract in which a vendor is expected to design, procure, and construct a power substation for $3,000,000. In this scenario, the organization agreed to which of the following types of contracts?
A.
A cost-reimbursable contract.
B.
A lump-sum contract.
C.
A time and material contract.
D.
A bilateral contract.
Your answer:
0 comments
Sorted by
Leave a comment first