Which of the following process models needs to complete each set of tasks in one phase before moving into the next phase in a project development life cycle?

A.
Procedural model
Answers
A.
Procedural model
B.
Evolutionary model
Answers
B.
Evolutionary model
C.
Spiral model
Answers
C.
Spiral model
D.
Waterfall model
Answers
D.
Waterfall model
Suggested answer: D