You are the business analyst for the NHQ Project. You have identified several stakeholders that need different types of information related to the requirements.
Which stakeholder would need detailed technical interface requirements?
A.
Project manager
B.
Regulators
C.
Testers
D.
Implementation subject matter experts
Your answer: