Question 212 - CBAP discussion
Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
A.
Influence diagram
B.
Project schedule network diagram
C.
Arrow diagramming method
D.
Time-scaled schedule network diagram