Which of the following is a visual decomposition of the program scope and the resources needed in order to create the things defined within the program scope?

A.
Resource breakdown structure (RBS)
Answers
A.
Resource breakdown structure (RBS)
B.
product breakdown structure (PBS)
Answers
B.
product breakdown structure (PBS)
C.
Budgeted Cost of Work Scheduled (BCWS)
Answers
C.
Budgeted Cost of Work Scheduled (BCWS)
D.
Work Breakdown Structure (WBS)
Answers
D.
Work Breakdown Structure (WBS)