Which of the following processes is must at the end of each project phase to determine the completeness of the project work and to gain the customer's acceptance to move the project forward?

A.
Scope verification
Answers
A.
Scope verification
B.
Inspection of key results
Answers
B.
Inspection of key results
C.
Quality control
Answers
C.
Quality control
D.
Phase gate review
Answers
D.
Phase gate review
Suggested answer: A