Question 257 - CBAP discussion
Which of the following processes is must at the end of each project phase to determine the completeness of the project work and to gain the customer's acceptance to move the project forward?
A.
Scope verification
B.
Inspection of key results
C.
Quality control
D.
Phase gate review