Question 258 - CBAP discussion

Report
Export

Which of the following is the comparison of planned project results with actual project results?

A.
Variance analysis
Answers
A.
Variance analysis
B.
Cost-benefit analysis
Answers
B.
Cost-benefit analysis
C.
Statistical Sampling
Answers
C.
Statistical Sampling
D.
Trend analysis
Answers
D.
Trend analysis
Suggested answer: A
asked 18/09/2024