A project's change in scope is assessed and a newly assigned business analyst (BA) is unsure how to communicate the findings and final decision to the wider stakeholder group.

In which of the following can the BA find this information?

A.
Stakeholder Communications Plan
Answers
A.
Stakeholder Communications Plan
B.
Business case
Answers
B.
Business case
C.
Business policies
Answers
C.
Business policies
D.
Governance approach
Answers
D.
Governance approach
Suggested answer: A