Question 290 - CBAP discussion
A new project has to implement a cyber security release in China, Italy, Germany, the United States, and Canada. The project is a $5 million initiative and must 'go live' in production in all countries on the same day and time to be effective.
Which of the approaches mentioned is suitable for this project based on the size and complexity?
A.
An agile and iterative approach
B.
A waterfall and dynamic approach
C.
A kanban and predictive approach
D.
A proven and tailored analysis approach