Question 292 - CBAP discussion
In performing the task of planning for business analysis governance for a software implementation project, the business analyst (BA) recommends that prioritization of requirements be done based on the amount of work that the project team is capable of delivering in a given period of time.
Which of the following techniques is the BA recommending?
A.
Negotiation
B.
Grouping
C.
Time Boxing
D.
Budgeting
Your answer: