A business analyst (BA) plans to hold a workshop next week to elicit requirements for a project. In an informal conversation, another employee mentioned that one of the attendees is likely to be unhappy about the project's impact on their work.

Which of the following techniques will the BA use to avoid disrupting the workshop?

A.
Elicitation Activity Plan
Answers
A.
Elicitation Activity Plan
B.
Collaborative Games
Answers
B.
Collaborative Games
C.
Stakeholder List
Answers
C.
Stakeholder List
D.
Risk Analysis and Management
Answers
D.
Risk Analysis and Management
Suggested answer: B

Explanation:

Reference: IIBA BABOK v3 (p. 84)