Question 470 - CBAP discussion
A business analyst (BA) has recently completed a comprehensive stakeholder analysis. Next, the BA would like to consider ways in which to ensure that the stakeholders remain engaged throughout the change strategy. Some of the considerations include timing and frequency, location, available tools, delivery methods, and the stakeholders' preferences. In which of the following plans would the BA document these considerations?
A.
Communications Management Plan
B.
Business Analysis Plan
C.
Stakeholder Analysis Plan
D.
Stakeholder Collaboration Plan