Which one of the following is not a general technique that a business analyst may use in the requirements verification task?

A.
Structured walkthrough
Answers
A.
Structured walkthrough
B.
Acceptance and evaluation criteria definition
Answers
B.
Acceptance and evaluation criteria definition
C.
Cost-benefits analysis
Answers
C.
Cost-benefits analysis
D.
Problem tracking
Answers
D.
Problem tracking
Suggested answer: C

Explanation:

Cost-benefits analysis is not a valid technique that a business analyst may use in the requirements verification task. The three techniques for requirements verification are acceptance and evaluation criteria definition, problem tracking, and structured walkthrough.

Answer B is incorrect. Acceptance and evaluation criteria definition is a valid technique for requirements verification.

Answer D is incorrect. Problem tracking is a valid technique for requirements verification. Answer A is incorrect. Structured walkthrough is a valid technique for requirements verification.