Question 447 - CCBA discussion
A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?
A.
Compare requirements with compliance requirements
B.
Determine the communication plan for requirements
C.
Reassure the project sponsor that testing will be conducted diligently
D.
Ensure requirements are traceable up to user acceptance testing