A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?

A.
Technical constraint
Answers
A.
Technical constraint
B.
Verified constraint
Answers
B.
Verified constraint
C.
Financial constraint
Answers
C.
Financial constraint
D.
Business constraint
Answers
D.
Business constraint
Suggested answer: D

Explanation:

A business constraint describes the limitations on the available solution - including financial, schedule, and resource limitations.

Answer C is incorrect. Financial constraint is not a category of business analysis constraints and assumptions. Answer A is incorrect. A technical constraint describes an architectural decision that may affect the allowed solution, such as development language, hardware, or software.

Answer B is incorrect. There's not a category of constraints called a verified constraint.