Tracy is a business analyst for her organization and she's gathered and identified the needed requirements for the solution scope. What must Tracy do before she can begin managing the requirements? Choose the best answer.

A.
Tracy must decompose the requirements in WBS.
Answers
A.
Tracy must decompose the requirements in WBS.
B.
Tracy must create cost-benefits analysis of each requirement to manage the benefits first.
Answers
B.
Tracy must create cost-benefits analysis of each requirement to manage the benefits first.
C.
Tracy must identify roles, responsibilities, and owners of the requirements to fully manage the requirements.
Answers
C.
Tracy must identify roles, responsibilities, and owners of the requirements to fully manage the requirements.
D.
Tracy must communicate the requirements to the stakeholders for their consent and approval.
Answers
D.
Tracy must communicate the requirements to the stakeholders for their consent and approval.
Suggested answer: D

Explanation:

Requirements must be communicated before they are managed. Tracy must communicate the requirements to the stakeholders for their consent and approval before managing the requirements.

Answer A is incorrect. Before Tracy decomposes the requirements, she should have the approval of the stakeholders.

Answer B is incorrect. To begin managing the requirements, Tracy needs the approval and consent of the stakeholders.

Answer C is incorrect. This isn't a valid statement, as the best thing to do is to gain the approval of the stakeholders first.