You are the business analyst for your organization and you're preparing the solution for your organization's review and implementation. Some of the requirements of the solution, however, must be inspected by compliance officers before the project and implementation can move forward. The requirements of the inspection can be best described as what?

A.
Bottleneck
Answers
A.
Bottleneck
B.
Requirements
Answers
B.
Requirements
C.
Cost-negativity
Answers
C.
Cost-negativity
D.
Constraint
Answers
D.
Constraint
Suggested answer: D

Explanation:

Requirements that require a compliance officer to be regulated and inspected are constraints that limit the project's options.

Answer B is incorrect. While these are requirements, the best answer is a constraint. Constraints limit the project's ability to move forward. A delay in the inspection can delay the project.

Answer C is incorrect. This isn't a valid term and isn't applicable to this scenario.

Answer A is incorrect. While some business analysts and project managers may call this a bottleneck in the flow of the project, the correct business analysis term for this is constraint.